Project:
Assessment and Optimisation of the Cooling Systems for a Large Data Centre
Location
London, UK
Client
Global Switch
Expertise
CFD
Keywords
Datacentre, Cooling, Wind Management
Manchester Simulation was engaged to deliver advanced CFD analysis for the external plant room at Global Switch London East, following the replacement of an air-cooled chiller bank in the Northeast Quadrant with a new set of water-cooled chillers and hybrid coolers.
Our team developed a detailed 3D model of all rooftop components and carried out simulations under a wide range of wind conditions and heat loading scenarios, in line with ASHRAE guidelines, to ensure full compliance. We also evaluated and modelled a number of mitigation strategies to confirm that the upgraded cooling system would perform reliably under worst-case operating conditions.
Despite the scale and complexity of the plant and equipment involved, the project was a success: the final design was validated through our simulations and was subsequently approved and implemented by the client.